JADUAL TENDER TENDER PRICE SCHEDULE
Jabatan Pengairan dan Saliran Malaysia (JPS)

NEGERI (state) Perlis
NO. TENDER (tender no) JPS/IP/BRE/04/2013
TAJUK PROJEK (project title) PEMBINAAN BAN PELINDUNGAN DAN SISTEM PERPARITAN DALAMAN SERTA KERJA-KERJA BERKAITAN DI MUKIM KG TASOH DI BAWAH PROJEK MENAIKTARAF EMPANGAN TIMAH TASOH, PERLIS, FASA 2 - PAKEJ 4
TARIKH TUTUP (closing date) 27 Mar 2014
JENIS TENDER (type of tender) Bumiputra
KELAS/KOD BIDANG (class/code) GRED : G7 KATEGORI CE PENGKHUSUSAN CE06 & M15
TIADA REKOD (no record)
Ruj (ref). Harga (price) Tempoh (period) Catatan (remarks)
1/61 41,001,110.00 18 Bulan
2/61 44,514,500.70 18 Bulan
3/61 50,912,945.00 18 Bulan
4/61 47,700,000.00 18 Bulan
5/61 54,901,670.00 18 Bulan
6/61 43,496,100.20 18 Bulan
7/61 51,383,565.00 18 Bulan
8/61 52,304,950.00 18 Bulan
9/61 47,444,300.70 18 Bulan
10/61 35,123,500.00 18 Bulan
11/61 48,800,000.00 18 Bulan
12/61 47,985,032.00 18 Bulan
13/61 38,866,698.00 18 Bulan
14/61 45,850,600.00 18 Bulan
15/61 45,012,300.50 18 Bulan
16/61 58,432,761.50 18 Bulan
17/61 44,500,000.00 18 Bulan
18/61 52,676,516.00 18 Bulan
19/61 50,168,709.00 18 Bulan
20/61 55,511,212.00 18 Bulan
21/61 47,538,908.00 18 Bulan
22/61 36,968,900.00 18 Bulan
23/61 50,383,383.00 18 Bulan
24/61 56,353,407.00 18 Bulan
25/61 38,334,485.00 18 Bulan
26/61 59,437,391.00 18 Bulan
27/61 76,995,502.00 18 Bulan
28/61 49,628,424.00 18 Bulan
29/61 39,628,000.00 18 Bulan
30/61 49,250,451.00 18 Bulan
31/61 51,388,000.00 18 Bulan
32/61 48,600,000.00 18 Bulan
33/61 44,517,042.00 18 Bulan
34/61 42,023,044.50 18 Bulan
35/61 49,699,020.70 18 Bulan
36/61 39,694,727.90 18 Bulan
38/61 47,446,003.75 18 Bulan
39/61 46,700,000.00 18 Bulan
40/61 39,615,278.00 18 Bulan
41/61 46,886,485.00 18 Bulan
42/61 45,515,500.40 18 Bulan
43/61 53,353,370.00 18 Bulan
44/61 59,491,133.80 18 Bulan
45/61 44,925,437.00 18 Bulan
46/61 49,838,838.00 18 Bulan
47/61 55,069,876.00 18 Bulan
48/61 34,949,630.00 18 Bulan
49/61 50,000,000.00 18 Bulan
50/61 45,448,096.90 18 Bulan
51/61 52,594,584.00 18 Bulan
52/61 43,999,551.70 18 Bulan
53/61 48,905,499.50 18 Bulan
54/61 52,178,501.00 18 Bulan
55/61 43,160,883.25 18 Bulan
56/61 44,141,184.00 18 Bulan
57/61 35,300,000.00 18 Bulan
58/61 43,818,000.00 18 Bulan
59/61 55,007,941.00 18 Bulan
60/61 34,774,400.00 18 Bulan
61/61 49,470,245.00 18 Bulan
37/61 49,193,949.50 18 Bulan